World Bank HQ

Electricity Network Reinforcement and Expansion Project (ENREP): Design Finalization, Supply, Installation (Construction) of MV & LV Over Head Distribution Lines and associated Distribution Transformers for Gonder and Adigrat Towns, Lot 3

Last update: Aug 23, 2019 Last update: Aug 23, 2019

Details

Locations:Ethiopia
Start Date:Jul 25, 2019
End Date:Jul 25, 2020
Sectors:Electrical Engineering
Electrical Engineering
Categories:Works
Funding Agencies:
Date posted:Aug 23, 2019

Associated funding

Associated experts

Description

Project ID: P119893

Project: Electricity Network Reinforcement and Expansion Project (ENREP)

Bid/Contract Reference No: ET-EEP-35635-CW-RFB

Scope of Contract: Design Finalization, Supply, Installation (Construction) of MV & LV Over Head Distribution Lines and associated Distribution Transformers for Gonder and Adigrat Towns

The Scope of work entails design finalization, supply and installation of:

1.  Rehabilitation and Upgrading of 242.63km, 15kV Overhead Distribution Lines;

2.  Rehabilitation and Upgrading of 127.86km, 0.4kV Overhead Distribution Lines;

3.  Rehabilitation of 40 no., 15/0.4kV, Pole Mounted Distribution Transformers;

4.  Supply and Installation of new 72 no., 15/0.4kV, Pole Mounted Distribution Transformers.

Duration of Contract: 12 Month(s)

Want to unlock full information?
Member-only information. Become a member to access projects awards, find the right consortia partners, subcontractors and more.